A widget assembly process was timed for 75 cycles and had an average of 1.5 minutes per piece. The p

A widget assembly process was timed for 75 cycles and had an average of 1.5 minutes per piece. The performance rating was 95%, and workday allowances are 10 percent. Determine the following:
a) Observed time
b) Normal time
c) Standard time
d) How might this information be used?